Residential Refurbishment · Archway, London N19

Full House Refurbishment

Value
£120,000
Duration
5 months
Location
Archway, N19
Architect
Private

Client Challenge

A compact 55m² flat needed a complete strip-out, improved energy performance, modernised layout and a high-spec finish - without losing control of programme or detail.

Bayocorp Solution

Full insulation upgrades to external walls and ceilings, installation of a new electric boiler and underfloor heating system, full electrical rewire with LED lighting, and a layout reconfiguration to create an additional bedroom.

Outcome

EPC improved from G to C - enhancing efficiency, reducing running costs, and increasing property value. The layout became more efficient and the finished space balanced usability, value and visual quality.

Honour's Acre West Sussex - drylining package project photo Honour's Acre West Sussex - completed construction project photo
Drylining & Construction · West Sussex

Honour's Acre - Drylining Package

Value
£140,000
Duration
5 months
Location
West Sussex
Client
Future Designer Homes

Client Challenge

Nine new-build houses required a consistent drylining, insulation, tape and jointing package - while coordinating around the main contractor and wider trades across all nine plots simultaneously.

Bayocorp Solution

The package was managed around programme milestones and quality expectations, maintaining consistent standards across all plots and delivering in coordination with the main contractor's programme.

Outcome

Works completed to a consistent standard across all nine units - maintaining quality, efficiency and a uniform finish throughout the development, delivered on programme.

Planning a refurbishment, fit-out or drylining package?

Tell us about your project - we respond within 24 hours on working days.

Brookview Road Streatham - completed project photo Brookview Road Streatham - second completed project photo
Joinery & Interiors · Streatham, SW16

Brookview Road - House Refurbishment

Value
£80,000
Duration
5 months
Location
Streatham, SW16
Architect
Private

Client Challenge

The home needed full internal decoration, improved storage and bespoke wardrobe installation - while maintaining finish consistency across the property.

Bayocorp Solution

Full internal redecoration throughout, alongside the design and installation of bespoke fitted wardrobes providing tailored storage solutions. Careful attention given to maximising space and usability.

Outcome

The property gained more practical storage, stronger room-to-room consistency and a cleaner interior finish - with integrated joinery enhancing both functionality and overall quality.

Fulham family home - refurbishment project photo Fulham family home - completed refurbishment detail
Residential Refurbishment · Fulham, SW6

Fulham Family Home - Four-Storey Refurbishment

Value
£235,000
Duration
6 months
Location
Fulham, SW6
Architect
Private

Client Challenge

A four-storey home needed a high-spec refurbishment, internal reconfiguration, modern services and a more efficient living environment - managed across all floors simultaneously.

Bayocorp Solution

New open-plan kitchen with underfloor heating, full heating system upgrade with combination boiler, reconfigured bathroom layouts throughout, new windows, flooring and internal doors, and full M&E installations.

Outcome

The home was modernised into a more usable, efficient and comfortable space - with a consistent high-quality finish across all trades, from structural works to decorating and joinery.

Sclater Street Shoreditch - completed flat refurbishment Sclater Street Shoreditch - second completed project photo
Residential Refurbishment · Shoreditch, E1

Sclater Street - Full Flat Refurbishment

Value
£65,000
Duration
5 months
Location
Shoreditch, E1
Architect
Private

Client Challenge

A two-bedroom flat required a full strip-out and refurbishment during the COVID period - requiring careful programme management, coordinated deliveries and contractor sequencing under significant external constraints.

Bayocorp Solution

Herringbone flooring throughout, bespoke monochrome kitchen, fully redesigned bathroom, full mechanical and electrical upgrades, EV provision, and an open-plan layout reconfiguration to maximise natural light.

Outcome

The property was opened up into a cleaner, more contemporary home - with stronger usability, improved natural light and a premium finish delivered entirely on programme despite COVID restrictions.

Your Project Next

Bring Bayocorp into the conversation early enough to protect the outcome.

Share your address, photos, drawings or outline scope and we'll help clarify what should happen next. We respond within 24 hours on working days.

We aim to respond to all enquiries within 24 hours on working days.